Case Study
5.715KW Solar PV Battery Ready in Torquay
Project Details:
Client Name: Torquay Golf Club
Industry: Commercial
Website: torquaygolfclub.co.uk
Location: Torquay
Project Completion: July 2025
£623
Estimated Annual Electricity Bill Savings *
27,607
Car km Avoided *
177
Tree’s Planted *
What were they trying to resolve:
With 2 installations under their belt, The golf club opted for a 3rd array on their Artisan Hut to not only to move further towards being carbon neutral but in this scenario make use of the government backed export scheme due to the hut’s low energy usage.
Services Provided:
Technical Survey
4G Online Monitoring System
K2 Flat Tile Mounting System
DC Electrical Connections
AC Electrical Connections
Full design and DNO consultation
NICEIC & MCS Certification
Battery Ready System
High Output JA Panels
What was the solution?
The south facing elevation of this building was smaller than the north, so we had to maximise the KW output of the area we had to work with. Like their previous systems we also opted for a hybrid inverter to add batteries in the future with minimal works. The idea was to allow the system to produce as much as possible so the golf club could benefit from the smart export scheme.
What was the result?
We chose the large 635W JA high wattage panel for this installation as this made the best use of the space available in kilowatt output per square meter. This allowed for a simple 9 panel area covering the south roof space. We also provided the golf club with a 4G data sim monitoring device. Due to the sites lack of WIFI this device allows the system to be connected to the internet and provide valuable data to the golf club on performance alongside their two other sites.
Get in touch!
If you would like a Solar Panel Installation in Torquay quote by our dedicated in house team who provide a full turn key service, then contact us today.
* These are estimated figures based on the system lifespan.